WIS 57/TEUTONIA AVENUE ROUNDABOUT TO OPEN TO TRAFFIC
The Wisconsin Department of Transportation (WisDOT) is scheduled to transition into winter shutdown along WIS 100 (W. Brown Deer Road) and WIS 57 (N. Green Bay Road) the week of December 19. Construction along WIS 100/WIS 57 will resume in early spring 2023. The following work is scheduled to take place as part of the project:
Tuesday, December 20
- WIS 57, along with the roundabout at Teutonia Avenue, is scheduled to open to traffic
- Ruth Place, at the intersection of WIS 57 (Green Bay Road), is scheduled to reopen to traffic
Thursday, December 22
- Kildeer Court at the intersection of WIS 100 (Brown Deer Road) is scheduled to reopen to full movements
WIS 100 median access to/from N. Deerwood Drive is now permanently closed. Motorists should utilize N. Deerbrook Trail to access Old Brown Deer Village businesses.
Travelers should be aware of the new traffic pattern, obey traffic control signs and pavement markings, and drive safely throughout the work zone.
All work is weather dependent and subject to change. The project team appreciates your patience during construction.